A job requires 480 usable units completed in 48 hours.

Material cost: $18 per unit started (material is consumed whether the unit is usable or scrapped..

Scrap rule: Defects are discovered after completion; scrapped units still consume full labor time and full material.

·         Worker A

o    15 units/hour

o    $36/hour

o    Maximum 16 hours

o    0% defect rate

o    If used, A must work first (hours 1–16 only..

·         Worker B

o    11 units/hour

o    $22/hour

o    8% defect rate

o    Unlimited hours

·         You may switch workers at any time (except A must be scheduled first if used..