Project Manager Training — Plumbing Phase
Purpose:Align homeowner style, designer intent, and building codes before anything is purchased or roughed-in.
Confirm fixture style, finish, compatibility with rough-in valves
Ensure designer selections match build budget
Capture official homeowner approvals early
✅ Upload fixture selections to the Detail Page with links & spec sheets
✅ Homeowner signs off on the Purchase Order Sheet
✅ Confirm flow rates, ADA requests, and specialty requirements
✅ Submit spec packet to plumber for review + redlines
PM Note:
The plumber doesn’t install style — they install function.Specs must be clear before they ever drill a hole.
Purpose:Prevent expensive reorders and last-minute scrambling.
Make comprehensive rough & finish fixture list
Verify supply chain lead times for specialty items
Prepare warranty & serial number tracking system
✅ Plumber signs off on fixtures + quantities
✅ Confirm trim kits match valve brands
✅ Document receipts in Expensify with category codes
✅ Label delivery stages: “Rough-In” vs “Finish”
✅ Create Backup Supplier Plan for shortages
Purpose:Ensure onsite framing and inspections support smooth rough-in.
Confirm all blocking for shower valves, ADA bars, wall-hung toilets
Input inspection dates into PM calendar
Protect the schedule by handling any prep issues NOW
✅ Track fixture delivery — delay notifications sent early
✅ Verify waste & vent penetrations required
✅ Stage dumpster plan for packaging + scrap
✅ Confirm no Change Orders pending before work begins
💡 Pro Tip:
Before the plumber arrives, perform a home walkthrough with the spec packet in hand — every fixture location must be ready.
Purpose:Ensure code compliance & working accuracy before walls close.
✅ Walk job with plumber AND homeowner to confirm heights & placement
✅ Ensure ALL rough-in valves, pans, drains are onsite
✅ Keep PM available for questions (plumbers will not wait)
✅ Approve routing of supply and waste lines (avoid structural issues)
✅ Photo every plumbing line → before drywall
✅ Upload photos to:
Basecamp: Trade Communication
Google Drive: Homeowner Documentation
Compliance Focus:Slopes, air admittance, trap arm lengths, fire-blocking around penetrations.
Purpose:Hold payment UNTIL all field requirements are validated.
✅ Blue Tape water/waste layout review
✅ Punch list created → plumber signs agreement on repair timeline
✅ Confirm Rough Plumbing Inspection PASSED
✅ Check for damage to framing, WRB, or electrical
✅ Office gives written approval before plumber is paid
🛑 Never rely on “plumber said it’s good” — inspections rule.
Purpose:Verify final function and protect finishes from water damage.
✅ Confirm ALL trim kits + finish fixtures onsite BEFORE plumber begins
✅ Check for matching finishes & correct models
✅ Protect tile, tubs, countertops from scratches
✅ Ensure wax rings + drain clamps installed cleanly
Leak Testing
✅ Run ALL fixtures — test every joint
✅ Confirm no movement in toilets or tub spouts
✅ Inspect all finish surfaces for damage
Purpose:Deliver complete water integrity & client satisfaction before releasing funds.
✅ Final Punch Walk with Installer and Homeowner
✅ Update as-built plumbing photos in Homeowner Manual
✅ Warranty registration + plumber emergency contact info
✅ Confirm Final Plumbing Inspection ✓
✅ Office approval to release payment ✓
🎯 Ultimate Goal:A completely verified, leak-free plumbing system documented for lifetime home ownership.
Thank you for completing this Session!
PM Milestone Confirmation✔ All fixtures approved & onsite✔ Rough-in photographed & inspected✔ No hidden leaks✔ Warranty documentation locked✔ Homeowner satisfied