Welcome To:
Project Manager Training — Concrete Phase
Purpose:
Understand design intent, verify structural requirements, and build a reliable cost + scheduling plan before ordering materials.
Study all structural details
Build a fully vetted material and labor scope
Confirm PSI & mix design requirements (e.g., 2500 PSI / 5 sack)
Establish schedule & inspection plan
Document existing conditions before build begins
✅ Confirm dimensions, rebar spacing, slab thickness, slope requirements
✅ Add all products and pricing to the budget with 5% contingency
✅ Enter every vendor & contact into the Sub Bid Sheet
✅ Verify plan for city inspections + which trades trigger inspection
✅ Upload before photos (grade prep, utilities, penetrations)
Time orders, secure logistics, and prepare the installer to execute efficiently without delays.
Prevent wasted labor from early deliveries
Confirm that nothing is missing before pour day
Document & track every receipt and detail change
Plan for unexpected shortages or traffic / access issues
✅ Schedule Concrete Truck + Concrete Pump arrival windows
✅ Confirm staging area for rebar, forms, embeds, and hardware
✅ Provide installers with your materials list for verification
✅ Add update notes to onsite printed plans as changes occur
✅ Keep plastic and curing protection onsite for emergency weather
✅ Prepare a Backup Supplier List for supply disruption
Lock in schedule, confirm safety & accessibility, and eliminate obstacles that could delay the pour.
Verify all under-slab systems are installed & inspected
Confirm team, drivers, inspectors are aligned
Finalize hardware, embed locations, and anchor bolt plans
Prepare homeowners and neighborhood for concrete delivery
✅ Confirm permit greenlights + inspection readiness checklist
✅ Verify concrete strength, quantity, and slumps ordered
✅ Confirm embed locations: anchor bolts, straps, sleeves, conduits
✅ Provide location for pump truck washout & cleanup
✅ Stage No Parking signs around site for the day prior
✅ Validate expansion joint layout with homeowner sign-off
✅ Set up water hose connection for finishing crew
Ensure proper installation, finish quality, cleanup, documentation, and accurate elevations before moving forward.
✅ Walk elevations with installer — verify forms, line, and grade
✅ Mark off slab & paths with caution tape
✅ Reinforce timeline expectations: no delays
✅ Keep dispatcher’s number ready for additional yardage
✅ Confirm inspection call + timing responsibility
✅ Blue Tape walk — punch list documented with photos
✅ Check for concrete splatter on structure — remove immediately
✅ Confirm:
✔ Elevations shot + recorded
✔ Foundation square & plumb
✔ Surfaces finished to spec
✔ Site cleaned & formwork removed
✅ Conduct final client walk & satisfaction acknowledgment
✅ Update budget + confirm office close-out
✅ Schedule follow-up work (sawcuts, curing checks, etc.)
✅ Celebrate team performance 🎉
Thank you for completing this Session!
PM Milestones Verified✔ Material & mix validated✔ Team & logistics aligned✔ Under-slab systems confirmed✔ Pour executed safely & cleanly✔ All dimensions documented✔ Jobsite cleaned & ready for framing