Project Manager Training — Drywall Phase
Purpose:Ensure structure, penetrations, mechanical inspections, and temperatures are correct before closing the walls.
Maintain 65°F minimum for proper drying + comfort
Review drywall thickness, fire ratings (garage, mechanical rooms)
Confirm:
Backing for towel bars, vanities, etc.
SIP panel door jamb width requirements
✅ Double-check interior doors ordered with correct jamb widths
✅ Review SIP joint coverage detail — fire & thermal requirements
✅ Confirm all insulation + sound batts + air sealing complete
✅ Clear QC sign-off on all MEP rough inspections
✅ Add any unique soffit framing or niches to Detail Page
Purpose:Order correctly, avoid material waste, and secure staging space.
Drywall type: Standard vs. Mold-resistant vs. Fire-rated
Ceiling board thickness
Corner bead type (rounded vs. square)
Verify delivery route for large sheets
✅ Subcontractor approves material list before the order
✅ Photograph delivery for condition + counts
✅ Create Drywall Storage Plan:
Avoid moisture-prone areas
Off ground with airflow
✅ Confirm weather protection on delivery day
Purpose:Ensure logistics, cleanliness, inspections, and trade handoffs are locked in.
Confirm scaffolding or lifts if needed
Clear walk paths + stair protection
Ensure no rework remains behind walls
✅ Final QC:
✔ All backing installed
✔ Fire caulking complete
✔ Low-voltage wiring secured
✔ Blocking for mirrors, rods, cabinets in place
✅ Inspection dates on PM calendar
✅ Provide heads-up to affected subs
✅ Confirm waste disposal plan for heavy debris
🚫 No drywall delivery until ALL MEPS are green-tagged.
Purpose:Support the installer and protect future finish quality.
✅ Walk job — verify sheet layout matches plans
✅ Approve drywall orientation for sound/acoustic walls
✅ Confirm:
Outlet + switch spacing clean
Window & door returns correct
✅ Photo all insulation + wiring and upload BEFORE walls cover
PM Tip:If a plumber, electrician, or HVAC tech returns after drywall → you pay twice.
Purpose:Achieve durable finishes and protect high-visibility areas.
✅ Confirm finish level:
Level 3 → garages
Level 4 → most interiors
Level 5 → high light areas (foyers, stairwells)
✅ Monitor:
Drying times
Humidity
Heater/dehumidifier setup
✅ Inspect corners, seams, bullnose, arches
✅ Protect tubs, windows, and floors from mud splatter
✅ Approve texture consistency before final spray or hand finish
📸 Photograph samples to ensure texture matches homeowner expectation.
Purpose:Deliver flat, clean walls that are ready for paint.
✅ Blue Tape walkthrough with installer
✅ Correct:
Dings
Reverse seams
Bowed studs appearing through board
Screw pops
✅ Sweep/clean site → dust containment before painting
✅ Confirm Drywall Inspection passed
✅ Office approval before payment release
🎯 Goal:Perfect surfaces → Zero repairs after primer.
Thank you for completing this Session!
PM Milestone Confirmation✔ Inspections passed✔ Proper finish levels achieved✔ No moisture or structural defects✔ Clean walls ready for paint